Takt Time Calculator

By Nicholas Williford, Lean Six Sigma Black Belt · About LimitLine

Takt time is how often one finished unit must come off the line to meet customer demand: takt time = available working time ÷ customer demand in that time.

Enter your available time and demand to get takt time. Add each station's cycle time to see which stations keep up (green), are close (amber) or are over takt (red), and how many operators the work needs. It runs in your browser.

Each calculation sends one anonymous count (the example or your own numbers). Never the numbers.

How It's Worked Out

This uses the same code as the LimitLine app (/source), checked when the page is built against the Lean Enterprise Institute lexicon example: 480 minutes a day and a demand of 240 a day give a takt of 120 seconds.

Questions

Is Takt Time the Same as Cycle Time?

No. Takt time is set by demand: how often the customer needs a unit. Cycle time is how long a station actually takes. A line meets demand when every station's cycle time is at or under takt.

Should Breaks Be in the Available Time?

No. Use only the time the line can actually work. Including breaks makes takt look longer than it is, and the line falls behind.

What If Demand Changes Every Day?

Use the average demand over a period you can level to (a week or a month), and adjust takt when the average moves. Leveling the mix is heijunka; the LimitLine app has a kanban and heijunka tool.

Sources

  1. Lean Enterprise Institute, Lean Lexicon: takt time
  2. M. Rother and R. Harris (2001), Creating Continuous Flow, Lean Enterprise Institute (operator balance charts)

The LimitLine Newsletter

About one email a month: new guides, tool updates and one practical SPC tip. Unsubscribe in one click.

We'll email you once to confirm before anything else is sent. Privacy