Learn · updated 2026-10-28
Takt Time and Line Balancing
Takt time is the available production time divided by customer demand: the pace the line must keep. Line balancing spreads the work so every station's time fits inside takt.
Takt time is the beat the customer sets; line balancing makes every station's work fit inside that beat. When one station is over takt, the whole line runs at that station's pace and the others wait.
Takt timeavailable time per day ÷ customer demand per dayMinimum operatorstotal work content ÷ takt, rounded upBalance efficiencytotal work ÷ (stations × slowest station time)Ruleevery station at or under takt
Worked Example
Two shifts of 450 available minutes, demand 720 units a day: takt = 2 × 450 × 60 ÷ 720 = 75 seconds. Four stations, eight tasks, 300 seconds of work in all (an illustrative line).
| Number | Calculation | Result |
|---|---|---|
| Total work | 75 + 65 + 100 + 60 s | 300 s |
| Minimum operators | 300 ÷ 75, rounded up | 4 |
| Balance efficiency now | 300 ÷ (4 × 100) | 75% |
| Idle time per cycle | 4 × 100 − 300 | 100 s |
Rebalancing
The theory says 4 operators (300 ÷ 75 = 4 exactly), but only if the work can be cut into four 75-second pieces. Keeping the tasks in their order, Assemble (70 s) can't share a station with Torque (30 s) without going over takt, so the tasks fit into 5 stations, none over 75 s:
Three Common Mistakes
- Using paid time instead of available time. Take breaks, meetings and planned maintenance out of the available minutes.
- Balancing to 100% of takt. Any wobble then stops the line; many plants plan stations at 85% to 95% of takt.
- Standard or best times instead of observed times. Time each task several times on the floor; use a typical (not best) cycle.
Sources
- Lean Enterprise Institute, Lean Lexicon: takt time