Takt Time and Line Balancing

By Nicholas Williford, Lean Six Sigma Black Belt · About LimitLine

Takt time is the available production time divided by customer demand: the pace the line must keep. Line balancing spreads the work so every station's time fits inside takt.

Takt time is the beat the customer sets; line balancing makes every station's work fit inside that beat. When one station is over takt, the whole line runs at that station's pace and the others wait.

Takt timeavailable time per day ÷ customer demand per dayMinimum operatorstotal work content ÷ takt, rounded upBalance efficiencytotal work ÷ (stations × slowest station time)Ruleevery station at or under takt

Worked Example

Two shifts of 450 available minutes, demand 720 units a day: takt = 2 × 450 × 60 ÷ 720 = 75 seconds. Four stations, eight tasks, 300 seconds of work in all (an illustrative line).

0255075100Load: 20 sLoadWeld: 55 sWeldSt 175 sGrind: 40 sGrindInspect: 25 sInspectSt 265 sAssemble: 70 sAssembleTorque: 30 sTorqueSt 3100 sTest: 45 sTestPack: 15 sSt 460 stakt 75 sEach bar is a station, stacked by task.
Station 3 (Assemble + Torque, 100 s) is over the 75-second takt, so the line can only make one unit every 100 s: 75% of the demand.
NumberCalculationResult
Total work75 + 65 + 100 + 60 s300 s
Minimum operators300 ÷ 75, rounded up4
Balance efficiency now300 ÷ (4 × 100)75%
Idle time per cycle4 × 100 − 300100 s

Rebalancing

The theory says 4 operators (300 ÷ 75 = 4 exactly), but only if the work can be cut into four 75-second pieces. Keeping the tasks in their order, Assemble (70 s) can't share a station with Torque (30 s) without going over takt, so the tasks fit into 5 stations, none over 75 s:

0255075100Load: 20 sLoadWeld: 55 sWeldSt 175 sGrind: 40 sGrindInspect: 25 sInspectSt 265 sAssemble: 70 sAssembleSt 370 sTorque: 30 sTorqueTest: 45 sTestSt 475 sPack: 15 sSt 515 stakt 75 sTasks kept in order; no station over takt.
After rebalancing every station meets takt. Four stations would need every one at exactly 75 s (100% of takt, which leaves no slack), so cutting work content with kaizen comes before cutting a station.

Three Common Mistakes

  1. Using paid time instead of available time. Take breaks, meetings and planned maintenance out of the available minutes.
  2. Balancing to 100% of takt. Any wobble then stops the line; many plants plan stations at 85% to 95% of takt.
  3. Standard or best times instead of observed times. Time each task several times on the floor; use a typical (not best) cycle.
Balance a line in LimitLineTakt time and a Yamazumi chart, with a suggested rebalance (a Pro tool; Free users can try it on the example).

Sources

  1. Lean Enterprise Institute, Lean Lexicon: takt time
  2. Lean Enterprise Institute, Lean Lexicon: Yamazumi board