OEE (overall equipment effectiveness) is the share of planned production time spent making good parts at full speed: OEE = Availability × Performance × Quality. 85% is the often-quoted world-class figure; many plants run nearer 60%.
Enter one shift's times and counts to get OEE, its three factors, and where the time went, step by step. It runs in your browser; nothing is uploaded.
How OEE Is Worked Out
- Planned production time = shift length − planned stops (breaks, meetings, no orders).
- Availability = run time ÷ planned production time, where run time = planned time − unplanned stops.
- Performance = ideal cycle time × total units ÷ run time: how close to full speed it ran while running.
- Quality = good units ÷ total units.
- OEE = A × P × Q, which is the same as ideal cycle time × good units ÷ planned production time.
The calculation uses the same code as the LimitLine app, published at /source. When this page is built it is checked against the oee.com worked example: Availability 88.81%, Performance 86.11%, Quality 97.80%, OEE 74.79%.
Questions
What Is a Good OEE?
85% is the world-class benchmark attributed to Seiichi Nakajima, made of about 90% Availability, 95% Performance and 99.9% Quality. Discrete manufacturers commonly measure around 60%. The useful number is your own trend and its biggest loss.
Should Breaks Count as Downtime?
No: planned stops come out before OEE starts, so they don't lower Availability. Count them only if your plant has decided to measure OEE against the full shift (sometimes called TEEP or utilization).
Why Is My Performance over 100%?
The ideal cycle time is set too slow. Use the fastest cycle the machine is designed or proven to run, not the planned or average one.
Sources
- oee.com, “Calculating OEE” (worked example)
- S. Nakajima (1988), Introduction to TPM, Productivity Press (world-class OEE figures)
The LimitLine Newsletter