Pareto Chart: Find the Few Causes Worth Fixing First
A Pareto chart sorts problems by how often they happen, biggest first, and adds a line of the running total. It answers one question: which few categories, fixed first, remove most of the problems? J. M. Juran named the idea the vital few and the trivial many, after the economist Vilfredo Pareto.
Percentcategory count ÷ total countCumulative %running total of the sorted percentsVital fewthe categories up to where the cumulative line reaches about 80%
Worked Example: 100 Defects on One Line
A month of rejected parts, grouped by defect type and sorted from most to least:
| Defect | Count | Percent | Cumulative % |
|---|---|---|---|
| Scratch | 40 | 40% | 40% |
| Dent | 25 | 25% | 65% |
| Chip | 15 | 15% | 80% |
| Stain | 10 | 10% | 90% |
| Burr | 6 | 6% | 96% |
| Other | 4 | 4% | 100% |
How to Make One
- Pick the categories (defect type, machine, shift, supplier) and one measure (count, cost or minutes lost).
- Pick one time period and collect the data for it.
- Total each category and sort from largest to smallest; group a long tail of small ones into “Other”, kept last.
- Draw the bars, then the cumulative percent line ending at 100%.
When There's No Vital Few
Sometimes the problems are spread evenly. Six categories of 9 to 12 problems each need 5 of the 6 to reach 80%, so “fix the top one first” removes under a fifth. That is a finding too: regroup the same problems another way (by machine, shift, supplier or cause) to find where they concentrate, or look for one cause behind several categories.
Three Common Mistakes
- Counting when cost matters. Ten scratches that are buffed out may matter less than one crack that scraps a part. Make a second Pareto by cost or minutes lost.
- An “Other” bar bigger than the top category. The categories are too fine or too vague; split “Other” before deciding anything.
- Mixing time periods or lines. Compare like with like, or a change on one line hides in the total.
Sources
- ASQ, “What is a Pareto Chart?”
- J. M. Juran (1951), Quality Control Handbook, McGraw-Hill